        • Production Orders: Planning What to Make
        • Production Execution: Recording What Actually Happens
        • Production Costing: Following the Money
        • Material Requirements Planning (MRP) - User Guide
        • Carton Manufacturing: Smart Material Planning for Corrugated Products
        • Carton Specifications: Defining Your Products
        • Carton Orders: From Customer Request to Production Plan
        • Carton Material Planning: The Optimization Engine
        • Carton Material Issues: From Warehouse to Shop Floor
        • .
      • e-commerce integration (Magento)
      • .
    • Examples
    • Reprocessing Transactions
    • Frequently Asked Questions
    • AI Generated Entity Flows Documentation

      • Core
      • Accounting Module
      • AI Module
      • Contracting Module
      • CRM Module
      • EGTax Reader Module
      • Freight Management System Module
      • Hospital Management System Module
      • HR Module
      • e-commerce Integration Module
      • Manufacturing Module
      • POS Module
      • Real Estate Module
      • Service Center Module
      • Supply Chain Module
      • .
    • Release Notes

      • 2016
      • 2017
      • 2018
      • 2019
      • 2020
      • 2021
      • 2022
      • 2025
      • .
    • Video Tutorials

      • Supply Chain Videos
      • Report Wizard Videos
      • Human Resources Videos
      • .

Material Requirements Planning (MRP) - User Guide

Introduction to MRP

Material Requirements Planning (MRP) is a production planning, scheduling, and inventory control system designed to manage manufacturing processes. It helps organizations ensure they have the right materials, in the right quantities, at the right time to meet production demands.

Why MRP is Important

MRP systems help businesses:

  • Reduce inventory costs by ordering materials only when needed
  • Improve customer service by ensuring timely delivery
  • Optimize production scheduling by planning material availability
  • Minimize stockouts through proactive planning
  • Coordinate purchasing and production activities

Core MRP Objectives

  1. Ensure materials are available for production and products are available for delivery to customers
  2. Maintain the lowest possible material and product levels in inventory
  3. Plan manufacturing activities, delivery schedules, and purchasing activities

MRP Concepts

Understanding these fundamental concepts is essential for effective MRP usage:

1. Demand

Demand represents the need for finished products or materials. There are two types:

  • Independent Demand: Demand from customers (e.g., sales orders, forecasts)
  • Dependent Demand: Demand derived from the production of other items (e.g., components needed to manufacture a product)

2. Bill of Materials (BOM)

A Bill of Materials is a comprehensive list of:

  • Raw materials
  • Sub-assemblies
  • Components
  • Parts
  • Quantities of each

...required to manufacture a finished product.

Example BOM Structure:

Product: Chair
├── Seat (1 unit)
├── Backrest (1 unit)
├── Legs (4 units)
├── Screws (16 units)
└── Wood Glue (50 ml)

3. Routing

A Routing defines the sequence of operations and resources required to manufacture a product:

  • Operation steps
  • Work centers/machines
  • Time requirements
  • Resource allocation

4. Lead Time

Lead Time is the time between initiating and completing a process:

  • Manufacturing Lead Time: Time to produce an item
  • Purchase Lead Time: Time from ordering to receiving materials

5. Safety Stock

Safety Stock is extra inventory held to guard against:

  • Demand variability
  • Supply delays
  • Quality issues
  • Forecast inaccuracy

6. Lot Sizing / Batch Size

Lot Sizing determines how much to order or produce:

  • Fixed batch size
  • Economic Order Quantity (EOQ)
  • Lot-for-lot (produce exactly what's needed)
  • Minimum order quantities

7. MRP Explosion

MRP Explosion is the process of:

  1. Starting with demand for finished products
  2. Breaking down (exploding) into component requirements
  3. Calculating net requirements at each level
  4. Scheduling production and purchases

MRP in Nama ERP

Nama ERP implements a comprehensive MRP system that integrates seamlessly with other modules. Here's how MRP concepts map to Nama ERP entities and processes:

Main Entity: MRP Document (سند تخطيط)

Navigation Path: Manufacturing > Material Resource Planning > planning raw materials Document

Arabic Name: سند تخطيط English Name: Planning Raw Materials Document

The MRP Document is the central entity that coordinates all material requirements planning activities.

Related Entities

EntityArabic NameEnglish NamePurpose
BOMمكونات منتجBill of MaterialsDefines product components and quantities
Routingعملية تشغيلOperation RoutingDefines production operations and resources
MRPSalesForecastingسند توقعاتSales Forecast DocumentCaptures predicted future demand
ManualDemandسند طلب يدويManual Demand DocumentCaptures manually entered demand
SalesOrderأمر بيعSales OrderRepresents actual customer orders

Prerequisites

Before using MRP in Nama ERP, ensure the following master data is configured:

1. Items Configuration

For each item, configure:

  • ✅ Primary UOM (Unit of Measure)
  • ✅ Manufacturing Lead Time (for manufactured items)
  • ✅ Purchase Lead Time (for purchased items)
  • ✅ Safety Stock settings
  • ✅ Minimum Order Quantity
  • ✅ Manufacturable Flag (check if item can be manufactured)

2. Bill of Materials (BOM)

For manufactured items, create BOMs with:

  • Component items and quantities
  • Batch size (lot size)
  • Associated routing
  • Specific dimensions (if applicable)
  • Default BOM flag

3. Routing

For manufactured items, create routings with:

  • Operation sequence
  • Resources required
  • Time estimates
  • Associated BOM (optional)

4. Warehouses

Configure warehouses with:

  • MRP flag enabled (to include in MRP calculations)

5. Scenarios (Optional)

Create MRP scenarios for:

  • Different planning horizons
  • What-if analysis
  • Custom available quantity calculations

6. Document Terms

Configure MRP document terms with:

  • Purchase order book/term
  • Production order book/term
  • Item request book/term
  • MRP purchase request book/term

MRP Document Workflow

The MRP process in Nama ERP follows this workflow:

Step 1: Create MRP Document

  1. Navigate to: Manufacturing > Material Resource Planning > MRP Document
  2. Click New to create a new MRP document
  3. Fill in header information:

Header Fields

FieldArabic NameDescription
CodeالكودAuto-generated document code
Value DateالتاريخDocument date
From Dateمن تاريخStart date for demand collection
To Dateإلى تاريخEnd date for demand collection
Aggregation Period Typeنوع فترة التجميعHow to group requirements (Daily, Weekly, Monthly, Quarterly, Yearly)
Req Qty Method Typeنوع الحقل المتعامل عليهFor forecasts: use Actual or Forecasted quantities
ScenarioالسيناريوOptional scenario for what-if analysis
Previous MRP Documentسند التخطيط السابقLink to previous MRP run (for rolling planning)
Purchase Doc Typeنوع مستند الشراءType of purchase document to generate (Purchase Order, Item Request, MRP Purchase Request)
Production Doc Typeنوع مستند الإنتاجType of production document to generate (Production Order, Production Order Request)

Aggregation Period

The Aggregation Period Type determines how demand is grouped:

  • Daily: Separate requirements for each day
  • Weekly: Group requirements by week
  • Monthly: Group requirements by month (recommended for most scenarios)
  • Quarterly: Group by quarter
  • Yearly: Group by year

Step 2: Collect Demand

After filling header information, click the Collect button (تجميع).

Collect Dialog Parameters

The system will prompt you to select which demand sources to include:

  • ☑️ Include Sales Orders (تضمين أوامر البيع)

    • Includes confirmed customer orders within the date range
  • ☑️ Include Manual Demands (تضمين الطلبات اليدوية)

    • Includes manually created demand documents
  • ☑️ Include Forecasts (تضمين التوقعات)

    • Includes sales forecast documents

Important

You must select at least one demand source. The system will show an error if none are selected.

What Happens During Collection

The system will:

  1. Search for demand documents within the specified date range
  2. Extract item requirements from each document
  3. Populate the Lines (التفاصيل) collection with demand sources
  4. Create Required Lines (الاحتياجات) by aggregating demand according to the aggregation period
  5. Calculate available quantities for each item

Step 3: Review Required Lines

After collection, review the Required Lines tab:

Required Lines Fields

FieldArabic NameDescription
ItemالصنفThe item required
Required Qtyالكمية المطلوبةQuantity needed
Required Onمطلوب فيDate when quantity is needed
DimensionsالأبعادSpecific dimensions (warehouse, locator, lot, size, color, etc.)
Total Availableالإجمالي المتاحCurrent inventory quantity
Predicted Purchaseالمشتريات المتوقعةExpected incoming purchases
Predicted Salesالمبيعات المتوقعةExpected outgoing sales
BOMمكونات المنتجBill of materials to use (if item is manufacturable)
Routingعملية التشغيلRouting to use (if item is manufacturable)

Manual Adjustments

You can manually edit:

  • BOM and Routing selections for specific items
  • Edited Net Required (الاحتياج الصافي المعدل): Override calculated net requirement
  • Edited Batches Count (عدد الدفعات المعدل): Specify exact number of batches to produce

Step 4: Analyze Requirements

Click the Analyze button (تحليل) to perform MRP explosion.

Save First

The document must be saved before you can run the analysis.

What Happens During Analysis

The system performs these calculations:

  1. For Each Required Line:

    • Fetches the BOM (if item is manufacturable)
    • Fetches the Routing
    • Calculates available quantity
    • Calculates safety stock
    • Determines net requirement
  2. Net Requirement Calculation:

    Net Requirement = Required Qty + Safety Stock - (Available Qty + Potential Available)
    
  3. Batch Size Calculation:

    • If BOM has a batch size, calculates number of batches needed
    • Adjusts net requirement to whole batches
    • Considers minimum order quantities
  4. MRP Explosion:

    • For manufactured items, explodes BOM to find component requirements
    • Recursively analyzes component requirements (dependent demand)
    • Considers lead times to calculate order dates
  5. Creates Analysis Lines:

    • One analysis line for each item-period-dimension combination
    • Links parent-child relationships for BOM explosions

Step 5: Review Analysis Results

After analysis completes, review the Analysis (التحليل) tab:

Analysis Line Fields

FieldArabic NameDescription
ItemالصنفItem being analyzed
Required Onمطلوب فيDate needed
Order Onتاريخ الطلبDate to order (considers lead time)
Required Qtyالكمية المطلوبةGross requirement
AvailableالمتاحCurrently available quantity
Potential Availableالمتاح المحتملExpected to be available
Safety Stockمخزون الأمانSafety stock requirement
Total Requiredالإجمالي المطلوبGross requirement before adjustments
Net Requiredالاحتياج الصافيNet requirement after considering availability
Net Required After Editالاحتياج الصافي بعد التعديلFinal requirement including manual edits
Batch Sizeحجم الدفعةProduction batch size
Batches Countعدد الدفعاتNumber of batches to produce
RemainingالمتبقيQuantity remaining after fulfilling requirement
BOMمكونات المنتجBill of materials used
Routingعملية التشغيلRouting used
Understanding Available Quantities

Available Quantity can be calculated from:

  • Current inventory in MRP-enabled warehouses
  • Previous MRP Document remaining quantities (for rolling planning)
  • Custom Scenario Query (if scenario is specified)
  • Available Qty Source Document (if configured)

Step 6: Review Planned Orders

The analysis automatically generates planned orders in two tabs:

Planned Production Lines (خطوط الإنتاج المخطط)

Contains production orders to be created:

FieldDescription
SelectedCheck to include in document generation
ItemItem to produce
QuantityQuantity to produce
DateProduction date (considering lead time)
BOMBill of materials to use
RoutingRouting to use
WarehouseProduction warehouse
Order TypeProduction Order or Production Order Request
DocGenerated document (after generation)

Planned Purchase Lines (خطوط الشراء المخطط)

Contains purchase orders to be created:

FieldDescription
SelectedCheck to include in document generation
ItemItem to purchase
QuantityQuantity to purchase
DatePurchase date (considering lead time)
SupplierPreferred supplier (if configured)
WarehouseReceiving warehouse
Order TypePurchase Order, Item Request, or MRP Purchase Request
DocGenerated document (after generation)

Filtering Planned Lines

Planned lines are separated into:

  • Manufacturable items → Planned Production Lines
  • Purchased items → Planned Purchase Lines

Items are classified based on the Manufacturable flag on the item master.

Step 7: Generate Purchase and Production Orders

Select Lines to Generate

  1. Review planned production and purchase lines
  2. Check the Selected checkbox for lines you want to generate
  3. Use Select All buttons to quickly select all lines in a tab

Generate Documents

Click one of these action buttons:

  • Generate Production Orders (إنشاء أوامر إنتاج)

    • Creates production documents from selected production lines
    • One document per line (by default)
  • Generate Purchase Orders (إنشاء أوامر شراء)

    • Creates purchase documents from selected purchase lines
    • One document per line (by default)
  • Gen Single Purchase Order (إنشاء أمر شراء واحد)

    • Consolidates all selected purchase lines into one purchase document
    • Groups items by supplier (if configured)

Document Terms Required

Ensure document terms are properly configured with books for:

  • Purchase Order
  • Production Order
  • Item Request
  • MRP Purchase Request
  • Production Order Request

The system will show an error if required books/terms are not configured.

After Document Generation

  • Generated documents are linked in the Doc field of each planned line
  • Documents are created in draft status (with @ symbol in code)
  • You can review and edit generated documents before committing
  • The Selected checkbox is automatically cleared (if configured)

Reviewing Generated Documents

Click the document reference in the Doc field to open and review the generated document.


Understanding MRP Results

Reading the Analysis Tab

The analysis tab shows the complete MRP explosion with all levels of BOM:

Level 0: Finished Product (from sales orders/forecasts)
    ├─ Level 1: Sub-assembly 1
    │       ├─ Level 2: Component A
    │       └─ Level 2: Component B
    └─ Level 1: Raw Material C

Hierarchical Relationships:

  • Parent Analysis Line ID: Links to parent in BOM structure
  • Master Row ID: Links back to the original required line
  • Parent BOM: The BOM that generated this requirement

Net Requirement Calculation Logic

The system calculates net requirements using this logic:

1. Start with Gross Requirement (from demand)
2. Add Safety Stock
3. Subtract Available Quantity
4. Subtract Potential Available (incoming purchases/production)
5. Result = Net Requirement (if positive)

If the item has a batch size:

6. Calculate batches needed = CEILING(Net Requirement / Batch Size)
7. Final Net Requirement = Batches Needed × Batch Size

If the item has a minimum order quantity:

8. Final Net Requirement = CEILING(Net Requirement / Min Order Qty) × Min Order Qty

Safety Stock Calculation Methods

Nama ERP supports three safety stock calculation methods:

1. Quantity-Based

  • Fixed quantity specified on item master
  • Simple and straightforward
  • Best for stable demand items

2. Periods Count - Current Period

  • Safety stock = Required Qty × Safety Stock Factor
  • Example: If required qty = 100 and factor = 1.2, safety stock = 20

3. Periods Count - Next Periods

  • Looks ahead at next N periods
  • Sums requirements from future periods
  • More dynamic, responds to demand patterns

4. Periods Count - Plan Average

  • Calculates average demand across all periods
  • Multiplies by safety stock factor
  • Smooths out demand variability

Configuring Safety Stock

Configure safety stock method on the Item master:

  • Safety Stock Calculation Type: Choose the method
  • Safety Stock: The quantity or factor (depending on method)
  • Order Limit: Fallback if safety stock is not set

Understanding Lead Times

Lead times affect the Order On date calculation:

Order Date = Required Date - Lead Time

For Manufactured Items:

  • Uses Manufacturing Lead Time from item master
  • Example: Required on March 15, Lead time = 5 days → Order on March 10

For Purchased Items:

  • Uses Purchase Lead Time from item master
  • Example: Required on March 15, Lead time = 10 days → Order on March 5

Lead Time Units

Lead times can be specified in:

  • Days
  • Weeks
  • Months

Ensure the UOM (Unit of Measure) is correctly set on the lead time field.


Generating Production and Purchase Orders

Document Generation Process

When you click generate buttons, the system:

  1. Validates Configuration

    • Checks document terms are configured
    • Verifies books have auto-coding enabled
    • Validates required fields
  2. Creates Documents

    • Instantiates appropriate document type
    • Sets book and term from MRP document term config
    • Copies dimensions from MRP document
  3. Populates Document Lines

    • For purchase documents: Creates purchase lines from planned lines
    • For production documents: Creates production order with BOM components
  4. Sets Document Details

    • Value date from planned line date
    • Warehouse from planned line
    • Supplier (for purchase documents)
    • BOM and routing (for production documents)
  5. Commits Documents

    • Automatically commits documents
    • Links generated documents back to planned lines
    • Updates MRP document status

Production Order Generation

For each selected production line, the system creates:

Production Order Header:

  • Item to produce
  • Quantity
  • BOM and Routing
  • Warehouse

Production Order Components:

  • Exploded from BOM
  • Quantities calculated based on production quantity
  • Considers yield and potency factors

Production Order Co-Products:

  • Copied from BOM co-products
  • Quantities proportionally calculated

Production Order Resources:

  • Copied from routing resources
  • Time calculated based on quantity

Production Order Operations:

  • Copied from routing operations
  • Sequenced according to routing

Purchase Order Generation

For each selected purchase line, the system creates:

Purchase Document Header:

  • Supplier (if specified)
  • Warehouse
  • Fiscal period

Purchase Document Lines:

  • Item to purchase
  • Quantity
  • Value date from planned date
  • Price (blank - to be filled manually)

Consolidating Purchase Orders

Use Gen Single Purchase Order to:

  • Create one purchase document for multiple items
  • Reduce number of purchase orders
  • Easier to manage with suppliers

All selected purchase lines will be combined into a single document.

Handling Generated Documents

After generation:

  1. Review Generated Documents

    • Click document reference to open
    • Review quantities and dates
    • Add pricing information (for purchases)
    • Verify BOM/routing selection (for production)
  2. Edit if Needed

    • Documents are created and committed automatically
    • Use "Start Editing" if changes are needed
    • Make adjustments
    • Commit again
  3. Track Generation

    • Generated documents have From Doc pointing to MRP document
    • MRP document tracks generated docs count
    • Can regenerate if needed (previous docs will be deleted if not committed)

Regeneration Behavior

If you regenerate documents:

  • Previously generated documents from this MRP document will be deleted
  • Only applies to documents that have From Doc = this MRP document
  • Committed documents in use (with transactions) will cause errors

Advanced Features

1. Rolling MRP Planning

Use Previous MRP Document to link MRP runs:

Benefits:

  • Carries forward remaining quantities from previous run
  • Supports continuous planning (e.g., monthly MRP runs)
  • Avoids double-counting requirements

Requirements:

  • Previous and current documents must have same Scenario
  • Previous document's To Date must be before current document's From Date

Example:

January MRP: From Date = Jan 1, To Date = Jan 31
February MRP: From Date = Feb 1, To Date = Feb 28, Previous = January MRP

February MRP will start with remaining quantities from January.

2. Scenario-Based Planning

Create scenarios for:

  • Different planning assumptions
  • What-if analysis
  • Custom availability calculations

Scenario Features:

  • Available Quantities Query: Custom SQL query to calculate available quantities
  • Potential Available Query: Custom SQL query for potential available
  • Do Not Divide Qty By Batch Size: Produce entire batch quantity rather than splitting into multiple production orders
Custom Query Format

Scenario queries should return a single numeric value representing the quantity.

Example query:

SELECT SUM(netQty)
FROM QtyTransLine
WHERE item_id = {itemId}
  AND warehouse_id IN ({warehouseIds})

The system will execute this query for each required line, passing item and dimension parameters.

3. Available Qty Source Document

Instead of scenario queries, you can create an MRP Available Qty Source document:

Features:

  • Manually specify available quantities per item/warehouse
  • Specify whether quantity is "Total Available" or "Predicted Purchase"
  • More controlled than scenario queries
  • Easier for users to understand and maintain

Usage:

  1. Create MRP Available Qty Source document
  2. Add lines for items with custom available quantities
  3. Select this document in MRP Document's Available Qty Source field

4. Manual Edits to Requirements

Override calculated requirements:

Edited Net Required (الاحتياج الصافي المعدل):

  • Manually specify exact net requirement
  • Overrides all calculations
  • Use for special cases or adjustments

Edited Batches Count (عدد الدفعات المعدل):

  • Specify exact number of batches to produce
  • Only works if item has batch size defined
  • Cannot be used with Edited Net Required

Edit Restrictions

  • Cannot edit net required if batch size > 0 (use edited batches count instead)
  • Cannot edit batches count if batch size = 0 (use edited net required instead)
  • Edits are validated on commit

5. Merge Planned Lines

Use the Merge action to combine planned lines:

Merging Production Lines:

  1. Select 2 or more planned production lines (same item and order type)
  2. Click Merge button
  3. System combines quantities into first selected line
  4. Removes other selected lines

Requirements:

  • Lines must have same Item
  • Lines must have same Order Type
  • At least 2 lines must be selected

When to Merge

Merge lines when:

  • Multiple small requirements for same item
  • Consolidating production runs
  • Reducing number of production orders

6. Dimension Handling in MRP

MRP respects item dimensions during planning:

Supported Dimensions:

  • Warehouse
  • Locator
  • Size
  • Color
  • Lot ID
  • Revision ID
  • Active Percentage
  • Inactive Percentage
  • Box/Package
  • Measures
  • Sub-item
  • Serial Number

Configuration: Manufacturing module configuration controls which dimensions are:

  • Considered in BOM/Routing Search
  • Used as aggregation keys in MRP planning

Example: If "Size" is enabled in MRP:

  • Red chairs and blue chairs are planned separately
  • Different BOMs can exist for different sizes
  • Requirements are tracked per size

7. Period-Based Safety Stock

For items with variable demand:

Configuration:

  1. Set Safety Stock Calculation Type = "Periods Count"
  2. Set Safety Stock = number of periods or factor
  3. Choose calculation method on MRP Document

Periods Calc Method Options:

  • Required In Current Period: Safety stock = Current period demand × factor

  • Next Periods: Safety stock = Sum of next N periods' demand

  • Plan Average: Safety stock = (Total demand / Total periods) × factor

Choosing a Method

  • Current Period: Best for steady demand
  • Next Periods: Best for growing demand
  • Plan Average: Best for fluctuating demand

8. Multiple UOM Handling

MRP works with items that have multiple units of measure:

Unit Used for MRP (configured in Manufacturing Configuration):

  • Base Unit
  • Primary UOM
  • Secondary UOM

All requirements are converted to this unit for planning, then converted back to item's primary UOM for document generation.

9. Handling Recurring Demand

For ongoing production schedules:

Approach 1: Monthly MRP Runs

  • Run MRP monthly
  • Use previous MRP document to carry forward
  • Generate orders for next month

Approach 2: Rolling Forecast

  • Update forecast document regularly
  • Rerun MRP with updated forecast
  • Adjust planned orders as needed

Approach 3: Manual Demand

  • Create manual demand documents for regular requirements
  • Include in MRP collection
  • Suitable for internal consumption patterns

Summary

Material Requirements Planning in Nama ERP provides a comprehensive solution for:

  • ✅ Planning material requirements based on demand
  • ✅ Exploding BOMs to determine component needs
  • ✅ Calculating net requirements considering availability
  • ✅ Generating purchase and production orders automatically
  • ✅ Supporting rolling plans and scenarios
  • ✅ Handling complex manufacturing environments

MRP Workflow Summary

1. Create MRP Document → Configure date range and parameters
2. Collect Demand → Gather from sales orders, forecasts, manual demands
3. Review Requirements → Check required lines are complete
4. Analyze → Run MRP explosion and calculations
5. Review Analysis → Verify net requirements and planned orders
6. Generate Documents → Create purchase and production orders
7. Execute → Review and commit generated documents

Key Success Factors

  1. Accurate Master Data: BOMs, routings, lead times
  2. Reliable Demand: Sales forecasts and orders
  3. Regular Planning: Run MRP at appropriate frequency
  4. Review Results: Don't auto-generate without review
  5. Continuous Improvement: Refine based on actual performance