Pushing Cost onto Real Estate Units

A contractor working on somebody else's land only ever needs cost per term: what did the blockwork cost, what did the plastering cost, are we inside the rate we tendered. A developer building units to sell needs something completely different — cost per flat. When flat 12 is handed over and invoiced, the cost of goods sold has to be flat 12's share of everything that was ever spent on the tower, and nobody spends money on flat 12: they spend it on the tower's blockwork, the tower's lifts, the tower's scaffolding.

That translation is what this bridge does. It takes the cost each document deposited against a contract term, finds the real estate unit that term is tied to, and records the cost against that unit — then pushes it down the estate hierarchy, so cost booked against "the tower" ends up apportioned to every flat in it.

If you are a pure contractor, nothing on this page will ever happen to you: leave the estate column on your contract terms empty and the bridge is a silent no-op.

It is a second, separate route into Real Estate cost

The Real Estate module has its own cost machinery — a catalogue of cost elements, each carrying its own distribution rule, and a cost voucher that spreads amounts over estates. That is described in Distributing Project Costs Over Properties, and it is the right tool for land, permits, lifts, marketing and every other lump sum a developer absorbs.

The contracting bridge is not that. It is an entirely separate path with its own stored table, fed automatically from construction cost, and requiring no voucher and no data entry of its own. Both routes end up as cost on the same units, and it is worth knowing which of the two put a figure there, because they are maintained by completely different documents.

Where the estate comes from

Every cost slice the module records carries the term code of a project contract line. The bridge needs to turn that term code into an estate, and there are exactly two ways it can, chosen by a single module setting:

SettingThe estate is read from
off — the defaultthe Estate column on the matching term line of the project contract
Calculate Estate Cost From Term Analysis Card onthe matching line of the term analysis card, using the cost slice's analysis term code

Either way, if the contract or the card cannot be found, or the matching line has no estate on it, the slice is simply not recorded against any unit. There is no error and no warning — the bridge only speaks when it has something to say. See Contracting Configuration for the setting itself, and note that with the analysis-card mode on, the estate column on the contract's terms grid is left empty.

When it runs: queued, in the background, never on a timetable

This is the fact that generates support calls, so it is worth being precise.

Every time a cost document is processed, and every time the contract-level cost distribution is triggered, the module queues a background task to do the estate work. Nothing is written to the estate at the moment you press Save. The units' cost figures appear once that task has been picked up and run.

It is not a scheduled job. Nobody has to set up a nightly run, and turning a schedule on will not make it happen sooner or more often — the trigger is always a document being processed. The task has its own view where a support user can see what is queued and what has failed, and it retries up to five times before it gives up and marks itself failed.

Cancelling a cost document works the other way round: its estate cost rows are removed immediately, along with the cost slices themselves.

The recursive split, and how to read the figures

Once the bridge knows the estate, it records the slice's full cost against it, and then walks down the estate tree. For each direct child of that estate:

child's share  =  child's weight  ×  parent's cost  ÷  total weight of all direct children

and the same thing happens again for that child's own children, all the way to the bottom. The weight is the estate's unit area by default; a module setting switches it to the estate's contracting estimated cost instead, for developers who price by expected cost rather than by area.

Read these figures one level at a time

The estate named on the term keeps the full cost, and each of its descendants also carries its share of the same money. The rows are not mutually exclusive: they are the same cost expressed at several levels of the tree. Adding them all together counts the same money once per level, so any roll-up, report or dashboard over this data must pick a level — the units, or the buildings, or the compound — and stay there.

Before hand-over and after

The bridge also decides when each slice happened relative to the unit's hand-over, and maintains two separate figures on every unit: contracting actual cost before hand-over, and contracting actual cost after it. The accounting treatment differs — pre-hand-over cost belongs in the unit's cost of sale, post-hand-over cost is after-sales or warranty expense — so the split has to be made somewhere, and it is made here.

The rule is straightforward, and it errs towards "before":

  1. a unit that has not been handed over at all — everything is before;
  2. a unit whose hand-over has no value date recorded — everything is before;
  3. a slice dated earlier than the hand-over — before;
  4. a slice dated later — after;
  5. a slice dated on the hand-over date itself — decided by which of the two was created first.

Both figures are refreshed on the unit every time the background task runs for any document touching it. The sales side reads them: the cost accumulated before delivery is what a sales contract can book as the unit's cost, and cost arriving afterwards is swept up separately — see Handing the Unit Over.

Worked example: a tower's plastering across twenty flats

Tower A for Al-Fanar Development, project contract PC-2026-001. This time we are the developer: the tower is ours and the twenty flats in it are for sale.

The estate tree beneath the tower:

EstateWhat it isUnit area
EST-TWRATower A, the building3,000 m²
EST-TWRA-01EST-TWRA-12twelve two-bedroom flats140 m² each — 1,680 m²
EST-TWRA-13EST-TWRA-20eight three-bedroom flats165 m² each — 1,320 m²

On the contract's Terms grid, term 3.02 Plastering names EST-TWRA in its Estate column. By the time the plastering is finished, material issues, subcontractor extracts, labour sheets and misc invoices have deposited 27,000 of cost against that term.

Each of those documents queued a task as it was processed. When the tasks have run, the bridge has recorded:

EstateParent rowCost
EST-TWRA27,000
each 140 m² flatEST-TWRA27,000 × 140 ÷ 3,000 = 1,260
each 165 m² flatEST-TWRA27,000 × 165 ÷ 3,000 = 1,485

Twelve flats at 1,260 is 15,120 and eight at 1,485 is 11,880 — 27,000 exactly, which is the sanity check worth doing when a distribution looks wrong. And note again what you must not do: 27,000 + 27,000 is not 54,000 of cost. It is 27,000, written down twice at two levels.

Now do the same for every other term on the contract that names the tower — the excavation, the concrete, the blockwork — and each flat's contracting actual cost before hand-over becomes the sum of its shares. Flat 3, still unsold, carries its 1,260 from plastering plus its share of everything else. Flat 17, handed over on 28 February, carries the shares of every slice dated before that day in its pre-hand-over figure, and anything dated after it — a defect put right in April, say — in its post-hand-over figure instead.

Which of those numbers is used, and where, belongs to the Real Estate module: Distributing Project Costs Over Properties for the estate cost picture as a whole, and Handing the Unit Over for the moment the pre- and post-hand-over distinction starts to matter. For where the 27,000 came from in the first place, see How Project Cost Is Built.