Stage Extensions

A Project Stage holds the promise: each phase, its targeted number of days, and the dates that follow from them. Phases then slip, and the question is what to do about it. Project Management (ECPA) answers it in a deliberate way — you never edit the schedule to absorb a delay. The targeted dates stay exactly as they were agreed, and the slippage is recorded as a separate document with a date, a size and a reason of its own.

That document is the Project Stage Extension, and it is the only thing in the module that can lengthen a stage. The Late Days Count column on the stage cannot be typed into; it is written from here.

Where to find it: Project Management → Projects → Project Stage Extension, under licence code ecpa.

The Screen

One page, and a short one. The header is the standard document set — document code and book, term, issue date, value date, five attachments and a description — plus one field that matters more than the rest.

The Project Stage Extension: From Document at the top, then a line per delayed milestone with its days and reason

From Document names the project stage being extended, and it has to be filled in first. The milestone picker on the lines below is limited to the milestones that appear on that stage — which is exactly what you want, since an extension can only lengthen a phase the stage already schedules, but it does mean the picker returns nothing at all while From Document is empty. If the lookup seems broken, that is almost always the reason.

The Details grid then takes one row per delayed phase:

ColumnWhat goes in it
Project MilestoneThe phase that slipped. Required, and it must be one of the stage's own milestones.
Late Days CountHow many days it slipped by. Required.
Stage Extension ReasonWhy, picked from the reason list. Optional.
DescriptionThe free-text version of why, for the detail the reason code cannot carry.

Below the grid sits the standard Dimensions group.

There is no requester and no approver field on this document. Whoever raised it is recorded by the system as its author, and if extensions need signing off at your site that is done through the system's general approval mechanism rather than through anything specific to this screen.

What Committing Does

Carry on the Marina Tower example from the stage page. The stage schedules Concept Design (30 days from 1 March), Schematic Design (45 days) and Tender Documents (25 days), running to a targeted end of 9 June. The client then takes ten extra days to sign off the massing.

  1. Raise an extension, set From Document to the Marina Tower stage, and add one line: Concept Design, 10 late days, reason Client approval delay.
  2. Commit it.
  3. Open the stage. Its Concept Design line now shows Late Days Count 10, and an expected end of 10 April against a targeted end of 31 March. Because the expected dates chain the same way the targeted ones do, Schematic Design and Tender Documents have each shifted ten days too, and the Consolidation group reads total targeted period 100, late days 10, total expected period 110.

Now suppose the structural consultant then loses four days on Schematic Design. Raise a second extension against the same stage, one line, Schematic Design, 4 days. After it commits, the stage reads Concept Design 10 late days, Schematic Design 4, total late 14, total expected period 114.

That second document is worth pausing on, because it shows how the arithmetic actually works. An extension does not add its days to whatever was there before. Each time an extension is committed, the system re-reads every committed extension raised against that stage, totals the late days per milestone, and writes the totals onto the stage's lines — putting zero on any phase no extension has touched. Then it re-chains the expected dates and re-totals the Consolidation group.

The pleasant consequence is that the numbers can never drift:

  • Cancelling an extension removes exactly its own days, no more and no less, and the remaining extensions keep theirs.
  • Correcting an extension — changing the days, or moving a line to a different milestone — leaves the stage holding the corrected total, not the sum of the old and the new.
  • Moving an extension to a different stage by changing From Document cleans up the stage it came from as well as updating the one it moved to.

Like the stage itself, the extension has no financial effect: committing it writes no ledger entry and moves no stock. Its entire purpose is those late-day numbers and the record of why they exist.

Reasons and Reason Types

The reason on a line comes from a two-level list, set up once and left alone.

Stage Extension Reason Type is the outer level — the family a reason belongs to. Typical setups have three or four: Client, Consultant, Contractor, Force majeure.

Stage Extension Reason is the reason itself, and it carries a Reason Type pointing at one of the above. So a firm might record:

ReasonReason Type
Late approval of design submissionClient
Late release of siteClient
Consultant comments returned lateConsultant
Drawing rework after design changeContractor
Weather stoppageForce majeure

Both screens are plain lookup files: a code, a group, an Arabic and an English name, attachment slots and dimensions. Nothing more, and — this is the point — nothing behind them. A reason does not change the number of days granted, does not restrict which stages it can be used on, and does not feed any calculation anywhere in the module. The two lists exist so that a year of extensions can be filtered and read: how many days did we lose to the client, and how many did we lose to ourselves? That question is answerable only if the reasons were picked consistently, which makes the setup worth doing properly even though nothing enforces it.