Order Executions

The execution sheet is the technician's document. One is produced for each machine on the maintenance order, it carries that machine's checklist, it has a start button and an end button that time the job, and it has a grid where the technician writes down the spare parts he actually fitted.

Everything in that sentence is true and useful. But there is one thing the sheet does not do, and getting it wrong is the single most expensive mistake in this module.

The execution moves no stock and no money

The spare-parts grid on an execution looks exactly like an inventory document — warehouse, locator, lot, serial, quantity. It is not one. Committing an execution creates no accounting entry and issues nothing from any store. The parts the technician records here stay in stock as far as the system is concerned until a maintenance invoice is saved, or until somebody presses Spare parts issue and saves the supply-chain document that opens.

Nothing checks that either happened. A branch that treats the execution as the stock-consuming document will have a warehouse that never reconciles, and the discrepancy grows with every job.

Required licence

crm-maintenance

The Order Execution screen

Producing the executions

Executions are never typed from scratch in normal use. On the committed order you press one of two buttons:

  • Create execution for all lines — one execution per machine line;
  • Create execution for selected lines — the same, limited to the machine lines you ticked.

Both require the order's document term to name an execution book and term; without them the buttons fail. Each execution is created and committed for you, its reference is written back into the order's machine line, and the order's status type moves to In Progress.

On 1 April 2026 the three machine lines of order MO-0513 produce three executions:

ExecutionMachineChecklistStartEndNet time
OEX-0771MCH-00311 Chiller No. 1Chiller Monthly Checklist (3 tasks)08:0011:303:30
OEX-0772MCH-00312 Chiller No. 2Chiller Monthly Checklist (3 tasks)11:4513:151:30
OEX-0773MCH-00318 Air Handling UnitAHU Monthly Checklist (3 tasks)14:0015:001:00
On site6:00

Which checklist arrives depends on one option on the order's term. Normally the tasks come from the machine line's own task template; tick Consider task templates tasks when creating executions and they come from the header template instead. See Task Templates.

Pressing the buttons again does not duplicate anything — the existing executions are updated in place.

What the technician sees

Main page. The order in From document, the machine, the task template, customer, technician, maintenance group, building, floor, room, the five machine classifications, warranty period type, current status, a from date and time pair, a to date and time pair, the calculated net time, a status (In Progress / Finished / Re-Open), currency and rate, six attachment slots, the maintenance contract, trouble level, trouble description, response time and two remark boxes.

Tasks grid. The checklist itself: a done tick, the task, a second task column, remarks and two attachments per line. Mark all lines done ticks the lot in one press.

Dysfunctions grid. Faults found while working, with the same old-warranty / new-warranty blocks as the order.

Spare parts and services page. Two grids — the parts fitted and the services performed — each with item, machine, quantity, unit of measure, unit price, discount, net value and the item dimensions.

On the three executions of MO-0513 the technician records SP-FLT-14 × 4 and SP-OIL-05 × 1 on OEX-0771, SP-FLT-14 × 2 on OEX-0772, and nothing on OEX-0773 — six filters and one oil in total, matching the order's grid exactly.

The three timing buttons

Start sets the status to In Progress and stamps today's date and the current time into the from pair if they are empty. End sets the status to Finished, stamps the to pair and computes the net time as the difference. Re-Open sets the status back to Re-Open.

All three only write values into the screen in front of you — the document is not saved by pressing them. If the technician presses End and closes the browser, nothing was recorded.

What committing an execution does

EffectResult
LedgerNone. There is no accounting logic on this document at all, and its document term has no accounting pages — only tax plan, taxable, modifiable tax and "allow editing header tax in details".
StockNone. See the box at the top of this page.
On the orderThe execution's status is written into the matching machine line's execution status; the order's status type becomes In Progress while any line is still running and Finished once they all report finished; the execution's current status is pushed onto the order.

Nothing else changes. In particular the contract entitlement is untouched — that was drawn down when the order was committed — and the machine's Last Visit Date is not updated, here or anywhere else.

Getting the parts out of the store

Two buttons on the spare-parts page open a supply-chain document pre-filled from the execution's lines:

ButtonOpens
Spare parts issue requestA stock issue request, which somebody then approves and issues
Spare parts issueA stock issue — the real inventory document

Both open in a pop-up as an unsaved draft. Nothing moves until you save it.

One route, not two

The maintenance invoice can generate its own stock issue from the same lines when its term says so. These buttons are an alternative to that, never a supplement — saving both takes the same parts out of stock twice, with no netting and no link between the documents. Decide once, per installation, which route you use, and train the branch on it.

A third button, Create sales quotation for priceless lines, collects every spare-part and service line whose unit price is empty or zero and opens a supply-chain sales quotation containing just those items. It is the "we need a price for this before we can bill it" helper.

Straight to the invoice

Create maintenance invoice on the execution opens an unsaved invoice draft: the header is copied, the execution's machine is promoted into an invoice machine line, and the spare-part and service grids come across. Review it and save it — see Maintenance Invoicing.

The execution validates nothing

An execution can be saved with no machine, no dates, no tasks ticked and no parts at all. There is no completeness rule of any kind on this document, so whatever discipline you want around it has to come from your own procedures. In particular, an execution reporting Finished is not evidence that the work was done, that the checklist was worked through, or that the parts left the store.

Reporting: none. This module ships no system reports, and this screen has no print form. The order screen carries an embedded list of the executions raised against it, which is the closest thing to a job-card report the module offers; beyond that, use the list view and its Excel export.